Client: Cory Environmental
Project Overview
Timeline
2020
Concept developed for forced, controlled cooling during site shutdowns, product designs, manufacturer approval achieved, control software written and site protocols established for safe delivery.
2021
Offsite test shutdown undertaken, concept proven.
2022
Onsite test shutdown successfully undertaken.
2023
Formally appointed by Cory / RRR.
Successfully completed first full site shutdown, forced controlled cooling of the turbine enabled the site to reopen days ahead of schedule.
2025
Appointed to deliver forced cooling for the next programmed site shutdown. Successfully executed, saving the site 80 hours of operational uptime.
Quote from Cory Group
The service received from Enercool has been impressive, they delivered the projects within the agreed timescales and worked closely with my team to ensure a smooth operation, which was safely delivered throughout each stage of the process
Jack Edwards, Cory Group